Fisherville Terrace 40B Development

Fisherville Terrace Aerial ImageApproved 40B starting construction

Timeline

  • NPC - Approved November 18, 2020 100 duplex units, 23 affordable units (2020)
  • Approved 42 Single-family units, 30 duplex units, 18 affordable units (2010)
  • Comprehensive permit approved December 3, 2010
  • 1-year extension to start construction to December 3, 2014
  • 1-year extension to start construction to December 3, 2015
  • 1-year extension to start construction to December 3, 2016
  • 1-year extension to start construction to December 3, 2017
  • 1-year extension to start construction to December 3, 2018
  • 1-year extension to start construction to December 3, 2019
  • 1-year extension to start construction to December 3, 2020
  • Construction to begin in Spring/Summer 2019
  • Meeting for NPC - elimination of drainage connection November 15, 2018 at 7:30 pm. Conference Room A
  • Continued to December 5, 2018 at 7 pm in Conference Room A
  • Continuation of NPC - elimination of drainage connection - Continued to January 17, 2019 at 8 pm - Conference Room A
  • January 17, 2019 application withdrawn without prejudice
  • February 28, 2019 - Board approved and signed the mylar plans
  • Meeting for NPC - change number of buildings from 57 to 50 and number of units from 72 to 100 - September 24, 2020 at 7 pm via Zoom Conference or live on Grafton Cable Channel 192 for Charter or 34 for Verizon
  • Continued to Thursday, October 22, 2020 at 7 pm via Zoom Conference or live on Grafton Cable Channel 192 for Charter or 34 for Verizon
  • Continued to Thursday, November 12, 2020 at 7 pm via Zoom Conference or live on Grafton Cable Channel 192 for Charter or 34 for Verizon
  • Granted: Thursday, November 12, 2020
  • NPC- Notice of Project Change - Size of Drainage Pipe on Main Street - opened January 12, 2023, Continued to February 16, 2023, Continued to March 16, 2023      -       GRANTED 3/23/2023

Contact Information for Affordable Units

Delphic Associates, LLC
Attn: Dawn
651 Orchard Street, Suite 308
New Bedford, MA 02744
Phone: 508-994-4100
Fax: 508-994-5100


Documents

  1. 1 Year Extension to 12-2-2019 (PDF)
  2. 1 Year Extension to 12-3-2014 (PDF)
  3. 1 Year Extension to 12-3-2015 (PDF)
  4. 1 Year Extension to 12-3-2016 (PDF)
  5. 1 Year Extension to 12-3-2017 (PDF)
  6. 1 Year Extension to 12-3-2018 (PDF)
  7. 1 Year Extension to 2020 (PDF)
  8. 10 Request to appear before the Board for 12.15.22 hearing Letter to Grafton Zoning Board (01223813xA4627).pdf
  9. Architectural Plans of Units 8-17-2020 (PDF)
  10. Cease and Desist Regarding Violation of Comprehensive Permit (DOCX)
  11. Comments from BOH 8-31-2020 (PDF)
  12. Comments from Chief of Police 9-15-2020 (PDF)
  13. Comments from DPW 9-14-2020 (PDF)
  14. Comments from DPW and State on Main Street Project (PDF)
  15. Comments from Graves Engineering 9-24-2020 (PDF)
  16. Comments from School Dept. 9-17-2020 (PDF)
  17. Comments from Sewer and DPW Regarding NPC (PDF)
  18. Cost Estimates, Unit Matrix, Location of Affordables Within Development 10-13-2020 (PDF)
  19. Emergency Contact List (PDF)
  20. Engineered Plans Dated 7-23-2018 (PDF)
  21. Final Approved and Signed Engineered Plans (PDF)
  22. Graves Comments on Intersection Site Distance (PDF)
  23. Intersection Sight Distance Analysis (PDF)
  24. Legal Notice for NPC - Elimination of the Drainage Connection (PDF)
  25. Letter From Applicants Attorney Regarding Cease and Desist (PDF)
  26. Letter from Attorney Dan Hill to Attorney Wickstrom Regarding Cease and Desist (PDF)
  27. Letter from SGWD 10-21-2020 (PDF)
  28. MADOT Main Street Plans (PDF)
  29. Memo From Graves Engineering Regarding Main Street Drainage Improvements and (PDF)
  30. Memo From Turning Point Regarding Drainage Pipe and Connection Into Main Street (PDF)
  31. NPC - Notice of Project Change (PDF)
  32. NPC - Request Change in Start and Arrival Time (PDF)
  33. NPC Request 8-17-2020 (PDF)
  34. Outline of NPC on the Plans Dated 10-10-2018 (PDF)
  35. Request for 1 Year Extension (PDF)
  36. Request to Withdraw NPC- Start and Arrival Time (PDF)
  37. Revised Design Layout of Development with All Duplexes 8-17-2020 (PDF)
  38. Revised Intersection Sight Distance Analysis (PDF)
  39. Revised Legal Notice for NPC - Change Number of Units and Buildings 9-1-2020 (PDF)
  40. Revised Storm Water Management Report 9-10-2018 (PDF)
  41. Signed and Filed Comprehensive Permit (PDF)
  42. Signed and Filed Decision for NPC (PDF)
  43. Fisherville Terrace_Modification_Final 1-25-22 All Duplexes including layout of affordable units in development
  44. Site Work Detail Cost Breakdown (PDF)
  45. Updated Traffic Report 10-19-2020 (PDF)
  46. Withdrawal Decision (PDF)
  47. NPC Request to appear before the Board for 12.15.22 hearing Letter to Grafton Zoning Board (01223813xA4627)
  48. Main Street drainage submittal package_3-9-23
  49. Comment from Fire on Fisherville Drainage
  50. DPW Comments on Fisherville Drainage
  51. Conditions for granting the requested from paul cournoyer memo
  52. Graves Engineering Comments on Drainage Plans
  53. Cost Estimate Main Street Drainage from Graves Engineering
  54. 13 fisherville signed and filed decision
  55. 14 cert of granting npc drainpipe

APPLICATION FOR AFFORDABLE UNITS